Inside the project

TGN: Mejillones bulk terminal

Unloading terminal (mainly coal) for attention ships Panamax of 80,000 DWT, and with a capacity of 6MTPA. The terminal consists of a jetty and a mechanized system.

The project consisted in the design of a  bulks unloading terminal (mainly coal) for attention ships Panamax of 80,000 DWT, and with a capacity of 6MTPA. The terminal consists of a jetty and a mechanized system, and PRDW was responsible for the conceptual, basic and details engineering of all the maritime and land works.

The maritime area considers a 140 m long unloading platform with 15 m wide, for two fixed unloading cranes (plus a future one) with a capacity of 900 TPH each, three mooring dolphins, 1 breasting dolphin, a buoy and an access trestle of 496 m long.

The mechanized system has a capacity of 2,250 TPH and consists of three bulk hoppers (mainly coal) and a system of two tubular belts of 800 and 520 m in length, to a delivery point, with its corresponding transfer tower, system dust mitigation, etc.

The engineering developed by PRDW included:

  • Definition of layout.
  • Study of the design wave conditions, wave penetration and the numerical modelling of ship at berth dynamics.
  • Operational downtime study.
  • Materials handling project.
  • Projects of maritime structures.
  • Project of land structures.
  • Electricity and instrumentation project.
  • Fire network design .
  • Architecture of office buildings, clothing house, dining rooms, others.
  • Drinking water, sewage, and other facilities.
  • Manoeuvring study.

PRDW supervised, checked and coordinated the studies of manoeuvrability, soils mechanics and oceanographic field measurements, 

S1095

Scope

Conceptual, basic and detailed engineering

Location

Chile, Mejillones Bay

Owner

Complejo Portuario Mejillones S.A.

Client

Belfi S.A.

Year

2008 – 2009