Inside the project

LNG Quintero: Unloading jetty

EPC contract for the design and construction of a new jetty for LNG vessels up to 265 000m³.

The project included:

  • 1,700 m long access trestle
  • Platform with unloading arms and topside
  • Mooring dolphins
  • Berthing dolphins
  • Gangway
  • Walkways
  • Sea water intake and discharge

The engineering input from PRDW-AV included the following:

  • Structural design
  • Hydrodynamic loads
  • Study of wave climate and extreme waves
  • Downtime study and moored ship dynamics modelling
  • Study of tsunami risk and modelling
  • Special seismic analysis

S1048

Scope

Preliminary, Basic and Detail Engineering

Location

Chile, Quintero Bay

Owner

GNL Quintero S.A.

Client

Belfi S.A.

Year

2007 – 2008